|
|
|
North Kesteven Report on LC December 2004 From Report Presented to North Kesteven District Council - Local Community Overview & Scrutiny Panel (Reproduced in full but certain areas are highlighted)2.12.04 Available as pdf along with LC's own Report via http://meetings.n-kesteven.gov.uk/ieListDocuments.asp?CommitteeId=289&CF=&MeetingId=2350&DF=&Ver=4
LEISURE
PARTNERING HALF YEAR REPORT - Client Officer's Report 1.0
Performance against Service Statements 1.1 The
service statements include a number of output measures, which the leisure
partner must achieve. These output measures have been agreed by the Client and
Leisure Connection and are evaluated on a quarterly, six monthly and annual
basis, following survey work and collection of data carried out by Leisure
Connection. 1.2 The
half yearly position for each of the service areas operated by Leisure
Connection is provided as Appendix A to this report. The format adopted for the
leisure partnering half yearly report is similar to the one that has evolved to
report the process of performance reporting for the Council. This includes two
levels of performance improvement action plans which have been identified in
consultation with Leisure Connection and where required explained in the body of
this report. 1.3 The
performance action plans are:- (stars relate to further documents
available at site listed) A Bold Star Symbol - This symbol is used to highlight where current levels of performance would indicate that corrective action is required for the end of the year target to be achieved. In such instances an action plan is required to identify the causes of the existing performance and the actions being undertaken to address these issues. A Transparent Star Symbol - This symbol is used to indicate where a current work programme is in place to deliver the target performance. No formal corrective action is required, the reported performance at the half year reflects the fact that either work is phased towards the second half of the year or alternatively performance is only marginally behind the plan and will be achieved in the remaining six months. 1.4 The
output measures for the key performance characteristics are provided in Appendix
A to this report. The following represent an area of underachievement. Natural World Centre –
Whisby K6A
The survey of visitors at the centre resulted in a poor sample response to the
number of visitors who rate the web site as relevant or informative due to many
visitors not using the web site. Leisure Connection are developing a web survey
available on line in order to improve this. There is considerable work required
to update the web site information, which was established as part of the
Objective 2 funding bid. North
Kesteven Centre There are two areas of underachievement in Exercise
referral and advice to clubs. The lack of information in these areas is
considered as an omission as historically there has been and continues to be an
high level of activity in these areas. The new business manager will look as these
areas as a matter of priority. 1.5
The following items are included for information Countryside Service A
requirement of the Countryside Ranger is to work with landowners, local interest
groups and the County Council to resolve barriers to the full use of the
Stepping out Network and other initiatives, and to seek to ensure that all legal
and permissive access agreements are maintained. 50% of disputes are to be
resolved within three months. There is only one outstanding issue regarding a
permissive agreement on the Blankney Barff Walk, which is currently with the
County Council. Hub K5C A minimum of 30 days of exhibition days to be devoted to exhibitions showing the link between current contemporary crafts and the traditional building craft processes using reference points within Navigation House and the wider Sleaford Townscape. The Head of Exhibitions is currently researching and investigating exhibitions for the roof gallery to meet this requirement and is planning to link into the opening of Navigation House. 2.0
Customer Forums 2.1 The
contract requires Leisure Connection to hold at least one user panel or clinic
for each service area each year. 2.2
Leisure Connection exceeds the contract requirement by holding four customer
forums per year at the sports and leisure sites and at least one at Whisby and
the Hub. 2.3 The
Arts team utilized the NKDC policy team to undertake an Arts focus group, which
was led by Emma Mablethorpe without team members present. This was a successful
forum, which identified a need for better publicity for arts events particularly
at the Terry O’Toole Centre. Participants
were complimentary on the arts events they had attended but felt the Theatre
required better marketing. 2.3 The
forums are held as a “drop in” clinic where customers are invited to discuss
their views with the management team over a coffee. Comments
from the Sleaford Leisure Centre and Northgate Sports Hall were mainly
concerning the new Harpers Gym, which was delayed, and praise for staff
particularly regarding the swim school. CLIENT OFFICER COMMENT ·The introduction of quarterly forums for Sport and Leisure exceeds the contract requirement. ·
Attendance
at the Northgate Forums has been poor and Leisure Connection is
considering a different
approach to
engage as many users as possible. ·
The approach taken by the
Arts team proved to be very
successful. 2.0
Community Forums held at the
North and South of the District once a
year and will this year take place during the Christmas markets at Sleaford and
North Hykeham. 3.0 Complaint Analysis 3.1 Leisure Connection provide a monthly return of customer comments and complaints which identifies any specific comments and the action that is taken in response to complaints. CLIENT
OFFICER COMMENT
· During the period it was noted that there has been a large number During the six month period the client office has
received 21 formal written / E mailed complaints as opposed to 28 for the same
time last year. These cover a range of issues. Late opening of facilities Cancellation of courses Housekeeping issues Poor quality of service NK Theatre Performances Issues around NK Bar furniture and bar staff NK Sports Hall Floor Stepping Out walks There were three areas, which received several
complaints:- 1.
NK Sports Hall Floor The
Sports Hall floor was out of action for six months due to the flooding incident
beyond Leisure Connection’s control, which inconvenienced the School, club
bookings and regular users. 2. Late Opening – Early Bird Swim – Sleaford
Leisure Centre There have been a number of incidents in which the center has not
been able to open on time for the early morning swimming session resulting in
complaints. In response to the formal action taken below, the Business Manager
has introduced a system to call in additional team members and has increased the
staffing of the session. 3. There has been a number of complaints received regarding service
issues such as cleanliness and staffing. The cleanliness of the upper bar area
at the North Kesteven Centre prior to Theatre performances and service during
intervals has been identified in particular. These
have been discussed with Leisure Connection and addressed by increasing staffing
and using the new foyer bar, which has improved the situation. 4.0
Contract Non Compliance and Default Notices 4.1 Where Leisure Connection are in default of a service statement requirement there are two courses of action, which are specified in the contract. Action Plan Process and Direct Rectification. ·
Action Plan Process Where an
action plan process is evoked Leisure Connection will submit an action plan to
the Council within 14 days of the event taking place. The Council will respond
within 7 days and either reject or accept the action plan submitted by Leisure
Connection. ·
Direct Rectification For
elements of the service statement that identifies a direct rectification as the
required action, Leisure Connection must remedy the situation within 5 days. ·
Default Notice There are
a number of criteria for which a default notice can be served, which represents
a fundamental breach of contract. If nine defaults are served in a six-month
period, the council can seek to terminate the contract. CLIENT OFFICER COMMENT ·
Action Plan Event In the six months period from April 1st – 31st October there has been 18 action plan notices issued. The majority of
action plans were issued following random inspections by the Client team for
failure to provide adequate marketing literature, failure to operate the service
in accordance with the Leisure Connection Quality Management System, not
adequately acknowledging third party funders on marketing literature and failure
to provide adequate contract survey and profiling information. ·
Direct Rectification There have been 8 Direct Rectification notices served,
which Leisure Connection have responded to within the specified time except one
which resulted a default. 1. Late Opening – Early Bird Swim – Sleaford
Leisure Centre Direct Rectification 4. 4th May 2004. Non-compliance with advertised/core hours. 2. Early Closure – Northgate Sports Hall Direct Rectification 5. 4th May 2004. Non-compliance with advertised/core hours. 3. Sports Outreach Direct Rectification 6. 7th May 2004. Failure to provide contracted input of hours. 4. Arts Team. Direct Rectification 7. 10th May 2004. Failure to provide contracted input of hours Arts administrative post. 5. North Kesteven Centre – Random Inspection Shared
Office Space Direct Rectification 8. 11th May 2004. Failed to maintain shared office space in accordance with service statement
requirements. 6. Contract Survey Requirements Direct Rectification 9. 12th May 2004. Failure to provide adequate survey information and analysis of visitor responses. 7. Late Opening –Early Bird Swim – North Kesteven
Centre Direct Rectification 10. 27th June 2004. Non-compliance with advertised / core hours. 8. Late Opening – Early Bird Swim – Sleaford
Leisure Centre Direct Rectification 11. 30th June 2004. Non-compliance with advertised / core hours. There have been a number of occurrences of late
opening at Sleaford Leisure Centre resulting in a series of complaints.
Although some have been unavoidable others have been because of a failure of team members to arrive on time.
Leisure Connection has responded by increasing staffing level for the early
morning sessions and adopting a call out protocol should a team member be unable to attend. ·
Defaults There have been three Defaults issued during the first
six months of this year. Default No 1 - 26th August 2004
Failure to provide an action plan for Action Plan 13 Provision of Contract Recharge Information Energy
Use – Theatre New Build Default No 2 - 26th August 2004
Failure to provide an action plan for Action Plan 14 Provision of Contract Recharge Information for
Carres Grammar School, LWT and County Council. Default No3 - 3rd`September.
Failure to rectify a direct rectification, in relation to survey information in accordance with the agreed action plan. 5.0
Contract Variation Requests 5.1 There
have been two contract variation requests one by Leisure Connection and one by
the Council. ·
Leisure Connection – Hub.
Contractor Request. Following
the six monthly inspection from the independent retail assessor, Leisure
Connection responded to her recommendation regarding makers information in the
retail area. It was requested that the makers name should always be displayed on
the work but that support information should be held at reception. - Request Approved 18th May 2004 ·
Increase Arts Team Core
Hours. Client Request. The funding for the Dance
Education post ended in September. It was discussed that
Leisure Connection should take over the post
from the District Council. The funding for the post to be taken from the income
generated by the post with the shortfall coming from the leisure partnering
development fund. Following consultation between the Client Officer and Contract
Manager this was agreed. - Request Accepted 26th August 2004 5.2
There are a number of service statement alterations that have been identified as
requiring amendments and these are included in the Annual Joint Scene Setting
report. 6.0
Random Inspections 6.1
During the period there have been seven random inspection visits across the five
sites. The inspections involve a tour of the facility with the Business Manger
or Duty Manager and an inspection of certain items as identified on the service
statements. The findings are summarised:- · Maintenance - Corrective Action Records are used as part of Leisure Connections Quality Management System (LCQMS) and identify the maintenance of defective items on site, with the time taken to rectify them. It is a requirement to rectify 70% faults within 3 days and this is audited during an inspection. In all cases the requirement is being achieved and exceeded and the performance over the half-year is identified for the sites in Appendix A. ·
The display of publicity literature across the sites has been poor. The requirement to carry information for all sites
and services including the retained services has not been achieved and an action plan has been required on several occasions. · The LCQMS provides clear guidance for staff training requirements in respect of lifeguard training. This is being maintained with all lifeguards trained to National Standards. ·
There have been some training issues due to turnover of team ·
The implementation of
Leisure Connection’s Quality
Management Systems was seen as a particular benefit to the service delivery
across the contract. It was recognized that it would take some time to implement
this, but it is evident from the random inspection s that the benefits of the
system are now being realized. Areas of Concern·
Marketing issues are still a
concern for both the Council and Leisure
Connection:-. o The Marketing Strategy, which is a contract
requirement for Leisure Connection to produce has been progressed but is still a
draft form and requires some work to enableit to be signed off. o There are still concerns over the marketing
activity, in particular promotional activity for the Hub and Whisby, which has
been identified by Leisure Connection and is being addressed. o The quality of literature produced for the contract
is high; however there have been occasions when the literature has arrived too
late to be effective. This is also the case with the sites general information
booklets, some of which have still not arrived. Team members have, on occasion
had to use photocopied information. o Leisure Connection has reviewed the position of
Marketing and Sales Manager and recognizing the importance of this position to
the contract have upgraded the position. A new Marketing and Sales Manager
starts in December. o Media relations continue to be an area of concern,
and the quality of the press releases is been raised as an issue by local media,
particularly in Sleaford. This has not been helped with the vacancy of the
Marketing and Sales Managers position. It is hoped this will improve now
the post has been filled. o We are disappointed at the apparent lack of evidence
of the promotion and proactive use of the Leisure Card for social inclusion. o Although the Council recognise the level of work that is required to establish marketing activity for the contract, it is hoped that Leisure Connection will significantly raise the profile of the services they deliver, and of the retained services which have been identified as a priority area. ·
The provision of survey information to provide the appropriate profile information is an important and fundamental
part of the contract requirement. The collection of user satisfaction surveys,
profile and visitor information is poor across the contract. Of particular
concern is the Hub Whisby and the Terry O’ Toole Theatre. ·
The delays of introducing new IT equipment has been frustrating and has caused some inconvenience to
customers. The Databox Theatre booking system is already functioning at NK
Centre and the Torex front of house system already installed at Sleaford is to
be installed at NK Centre in December. There are a number of site and service web sites,
which are the responsibility of Leisure Connection and need to be reviewed and
updated during the next six months. Work is progressing. 7.0 Areas
of Achievement ·
The introduction of Leisure
Connection’s branded services has been a
particular benefit to the contract. Camp Energy – Leisure Connections activity
programme which has been rolled out across the contract has proved to be very
successful again this year and included very popular Sports Outreach courses and
Performing Arts Summer School at North Kesteven Centre and for the first time at
Northgate Sports Hall. Aqua Action the swim school product has seen an
improvement in the quality provided with reduced numbers to teachers and is
linked to the
ASA
national programme. Harpers the fitness will be relaunched at Sleaford in
January with the refurbished currently under way. There
have been significant improvements in a number ofservice areas.:- o Arts NK
– Encouraging developments in large community and environmental arts projects,
which have engaged local communities. In Visual Arts the Branston Gateway
project, the Nocton trail and the Whisby trail. In performing arts, the summer
school events which included a week at Northgate Sports hall, the continued work
of Dance NK and the Rural Arts programme were some of the highlights. The market
towns week project involving performers and the burning of fire sculptures made
by School students and firework display. o
Countryside NK - the work of the Countryside Ranger developing a very successful
series of health walks and developing a programme for conservation volunteers
for Lollycocks field. o Hub –
The varied exhibition programme has been very well received by visitors and the
specialist panel. The international “Jet Set” conference organized by the
Head of Exhibitions involved 40 delegates in a two day event, which included an
evening dinner at Whisby o The
education programme at the Hub has seen over 4000 participants with 150 projects
spanning 200 activity days. o Natural World Centre –
The launch of the Leisure Connection Venue Connect brand has seen the first
wedding reception to be held at Whisby as well as a number of other catered
events. The joint working with the Wildlife Trust is helping to make further
improvements to the site as
a whole. ·
A good example of joint
partnership working was the operation of the
pilot mobile skate park project. This involved the Client team, Sports Outreach
and Northgate Sports Hall. Leisure Connection was responsible for the equipment
set up and supervising the activity. 277 skaters were able to attend 30
operational days at 7 different parish / towns locations. The highlight was a
Skate Board competition at Northgate Sports Hall, which attracted 52
participants. ·
Capital Works. The
refurbishment of the Dance Studio and
Gymnasium, which is being undertaken by Leisure Connection at Sleaford has
started. As part of this project Leisure Connection is project managing the
Landlords investment programme for the changing rooms. Once the project is
completed the company will formally re-launch its fitness brand “Harpers”
which is due to commence in January. Mike Lock
Client Officer |
|
|