Important Dates:
19721973 - Coal Board presents paper/seismic exploration
August 1974 - application to work Barnsley seam submitted
1975 - planning enquiry
April 1976 - planning permission granted "in National interest"
June 1977 - ground freezing for Wistow shafts
March 1978 - drift drivages at Gascoigne Wood; shaft sinking at Riccall and Stillingfleet
1979/80 - Wistow reaches Barnsley seam
1983 - Wistow starts production
November 1985 - Gascoigne Wood surface complete
1987 - Stillingfleet connects to Gascoigne Wood south tunnel
June 1987 - south spine tunnel - drivage complete at 12.2 km
December 1987 - Wistow sets new European record
1988 - Riccall, Stillingfleet, Whitemoor commence production
January 1991 - North Selby comes into production
1991 - Wistow Mine - 711 men produce 108,700 t in 1 week
(January 1995 - purchase of British Coal by RJB)
September 1995 - new European output record - Wistow - 200,743 tonnes in one week
(Back to home page)
Back to Gascoigne Wood page
Gascoigne Wood Figures:
Best annual output: 12,090,516 tonnes
Daily ROM: 75,760 t
Shift ROM: 28,625 t
Weekly ROM: 442,315 tonnes
Most trains per shift: 22
Most trains per day: 51
Most trains per week: 297