|
|
|
Lewisham See Save Ladywell Pool for details of their campaign and much other information. Also see www.londonpoolscampaign.com
Independent Review Of Downham Contract As you will see further below, in September the Mayor of Lewisham was peeved at the delays in the Private Finance Initiative deal for Downham Lifestyles. Penny Badcoe, an independent consultant with expertise in PFI, was asked by Lewisham Council to consider the procurement process, investigate reasons for delay, and to identify lessons learned." She dated her 34 page report "January 2006". Ms Badcoe reported that the project took "just over four four years in procurement from the approval of the Outline Business case". She notes this is not unusual in PFI deals and particularly in a complex and innovative one. One issue was that a Dutch bank dropped out from the scheme and replacement finance had to be found. While the council is not seen to be without fault there are some telling paragraphs concerning the Linteum / Leisure Connection Consortium. The consortium "...were negotiating two contracts concurrently, and from the summer of 2004 onwards they prioritised work on the Brent deal up until it closed during the following March. This was discussed extensively between LBL (Lewisham) and Linteum at the time, and indeed it was understood that Linteum was open about their strategy. However, the timing and certainty of communication on this point is somewhat unclear between the parties... The consortium sought to reassure LBL staff and advisers that this approach would make the eventual closure of the LBL deal easier. This was suggested on the basis that the Brent scheme as much simpler, involving only leisure provision and a single client, and that issues resolved in Brent would be applicable to the LBL project. In the event , this did not happen because the LBL project was different and the Brent approach was not considered by LBL and its advisers to be applicable. It might even be argued that attempts to apply Brent caused further delay in the final stages of the LBL negotiations. Once again there was lack of clarity about communication... Although it is difficult to be precise, and impossible to disaggregate the impact of individual factors on the overall process, it is likely that the project would have been delivered several months earlier, if there had been no change of bank and no Brent deal running concurrently ." (p10) The concluding paragraph makes clear that the history of the procurement is a threat to the completion of the project. "It is vital that any negative feelings and past difficulties are now set aside in order that all parties may work effectively together on the construction phase... This joint working should include liaison with the press to ensure the best possible publicity for the launch of Downham Lifestyles. Although I remain concerned about ongoing project management as the build phase progresses, I do believe that there is a collective will to do so." Time will tell and whatever happens the citizens of Lewisham will pay. Thanks to the two people who anonymously posted LCW the report. PB Press report on the above story appearing a week after LCW account. News Shopper 7.2.06 http://www.newsshopper.co.uk/news/lewgreennews/display.var.684305.0.delay_blamed_on_communication.php
Reproduced in Full 20.9.05 From This is Local London http://www.thisislocallondon.co.uk/news/headlines/display.var.631888.0.mayor_demands_answers_after_contract_delay.php LEWISHAM Mayor Steve Bullock has asked officers to review the contractual process behind the Downham Lifestyles Project.
Mr Bullock last week admitted he is "disturbed" the contract for the £16m leisure development took nearly two years to sign.
He has now asked council chief executive Barry Quirk to lead an investigation into what went wrong. Mayor Bullock's now accepts something went wrong whereas in March (see below) he was adamant that "every effort" had been made by officers. Or is he accepting some of the problems stemmed from the councillors most involved in ignoring residents? PB 11.10.05 Lewisham council is £4,576,000 overspent before the building of a new centre has started. For this the public will end up with a pool 25% shorter than the existing pool, no extra lanes and a smaller learner pool. This is what the Mayor has described a "flagship, state of the art swimming centre". PB 6.9.05 From News Shopper 25.5.05 http://www.newsshopper.co.uk/news/lewgreennews/display.var.599600.0.still_no_start_date_for_leisure_centre.php Still no start date for leisure centre by Paul Revel (reproduced in full) THE COUNCIL has admitted it cannot impose fines against a firm, further delaying a long-awaited leisure centre. At a full council meeting last week, Councillor Mark Morris demanded to know why a start date for the Downham Lifestyles Project leisure centre has still not been set despite already being more than two years late. The project, which includes a swimming pool and a library, was announced in the borough's Labour Party manifesto which claimed it would be up and running by 2004. But unless negotiations are wrapped up in the next few days, it is unlikely the project will be completed before 2007 almost three years late. Cllr Morris asked the question two months after contractors Leisure Connection (LC) missed a target date for finally signing contracts on March 11. Lewisham mayor Councillor Steve Bullock admitted the delays were caused by Private Finance Initiative (PFI) contractors LC making slow progress. He said LC has over-reached itself by bidding for another PFI project, instead of focusing on its commitments at Downham. Cllr Bullock also said no financial penalties can be imposed against LC while negotiations are continuing. The Downham Lifestyles Project, to be managed by LC for 30 years at a cost to the council of £70m, also includes a fitness studio, a gymnasium, a community room, a creche, a music and drama studio and two GP surgeries. Councillor Morris said: "Something has gone wrong and it's bitterly disappointing. While this drags on, thousands of people are missing out on these facilities." He says the old pool, built in 1937, was very popular before it closed in 1995 and 101,000 people passed through its turnstiles in 1994. Cllr Morris says the leisure facilities are vital for residents of all ages. He said: "I am not going to give up. Lessons have to learned and somebody needs to be held responsible. A joint statement from Leisure Connection and Lewisham Council said all parties were doing "everything possible" to bring the negotiations to a conclusion. The council is attempting to finalise the deal as soon as possible. From ContractJournal.com http://www.contractjournal.com/home/Default.asp?type=2&liArticleID=46039&liSectionID=1&liDF=1 13 Apr 2005 Lewisham PFI deal faces further delays (reproduced
in full) Question asked at Lewisham Council meeting on 2.3.05
http://snipurl.com/dp1h Will the Mayor provide an update on the progress of the Downham Lifestyles Project and also provide estimated opening dates for each of the different services involved in the overall project. Reply: Despite every effort having been made by officers, negotiations with the preferred bidder, Linteum / Leisure Connection, have slowed due to their concentration on completing another leisure PFI project which, for various reasons, has taken much longer to finalise than anticipated. The representatives of the preferred bidder consortium negotiating this other project are exactly the same as for the Lewisham project. This has resulted in the preferred bidder attempting to balance resources between the two projects. With one project manager for the consortium handling both projects this has led to a pinchpoint in negotiations with the consortium. We have made clear our dissatisfaction on how the consortium has handled this. The preferred bidder is now focussing its team on closing the Lewisham project and a target date of 11 March for completion of negotiations has been set for all parties to achieve. Working on the basis of a targeted financial close on 11 March the anticipated opening of the Park will be Autumn 2005 with the Lifestyles Centre a year later in late Summer 2006. More precise dates for the various opening dates will be confirmed as the final elements of the deal with the preferred bidder are finalised in the coming few weeks. Efforts have been made on both sides not to delay the eventual opening of the Lifestyles Centre. Significant preliminary enabling works have therefore been approved with some site preparation works already completed e.g. ducting onto site, purchase of steel and other advance purchases of certain construction materials. The constructor has also been permitted to complete hard standings for the builders’ huts, a temporary road and parking space on the main site. Once the contract is awarded a meeting will be arranged for the public to hear from the contractor’s representatives about the building works programme. I think the contract that took precedence is the one in Brent. PB |
|
|