2007

All the repairs to the bridges have been completed and track has been laid across them.  The track has been jacked and packed from World's End to the north end of the cutting.  During the August Bank Holiday weekend the last four panels in this section were laid.  This takes us seven panels north of Langford Bridge, and will give us sufficient clearance to be able to operate over this section once it has all been jacked and packed with ballast.  We are now just four panels of track away from Lee Moor Crossing.

We have purchased materials to build a new crossing over the cycle path and the gates are also being made.  Plans for the Level Crossing are being drawn up and will be submitted to the relevant authorities.


Go to Top

Back to Projects and Latest News page.

Vanguard south of Langford Bridge
Vanguard south of Langford Bridge, January 2007.
Track over Langford Bridge
Track is now laid over the Bridge,
May 2007.
Track nearly to Lee Moor Crossing
Four more panels of track are laid north of Langford Bridge, Aug. 2007.
13002
13002 on a test train north of Langford Bridge, June 2007.
D.M.U. on test train
D.M.U. near the 1 mile post, measured from the original Tavistock Junction.
Newly arrived rail
More rail is delivered to the Railway.
  Lee Moor Crossing gates
The gates for Lee Moor Crossing are under construction.
 