2008

The line has been re-laid from Langford Bridge to just short of Lee Moor Crossing using concrete sleepers and flat bottom rail.  After a lot of jacking and packing in some areas the line was ready for inspection.  In the spring, Inspectors from the Office of Rail Regulation visited the Railway, after we submitted the relevant paperwork to them, and they subsequently gave us approval to operate passenger trains to Lee Moor Crossing.  This gives a run of nearly three-quarters of a mile.

Work has started on the construction of a new level crossing that will enable the cycle-path, on the old Lee Moor Tramway trackbed, to cross our line as we relay it towards Plym Bridge.


Go to Top

Back to Projects and Latest News page.

approaches to Lee Moor Crossing
Laying the track up to Lee Moor Crossing
 January 2008.
approaches to Lee Moor Crossing
West side rail has been laid on to the sleepers and clipped into position.
approaches to Lee Moor Crossing
After jacking and packing the track is boxed in with ballast.
March 2008.
Albert at Lee Moor Crossing
Albert almost at Lee Moor Crossing.
The new level crossing will be built here.
July 2008.
Lee Moor Crossing gates
The gates for Lee Moor Crossing
under construction.
Lee Moor Crossing panel
13002 sits on the newly laid track panel
where Lee Moor Crossing will be built.
November 2008.